The bottleneck in production is some scarce resource that reduces the production capacity of the whole chain. The bottleneck needs to be efficiently managed to ensure profit maximization and enhanced business efficiency.

It’s called a bottleneck because the neck limits the volume of water to be stored in the bottle. The production bottleneck similarly limits the quantity of the units to be produced in the production process.

How does it work?

Businesses usually face some challenges that bring limitations in their capacity to operate and grow. These limitations can be short or long terms in nature. The short-term limitations usually do not present a greater challenge. However, the cumulative effect of the long-term bottleneck is adversely higher on the business growth and efficiency.

An example of a short-term limitation is the skilled employee going on leaves. This might create problems in the production if an adequate replacement is not available within the organization. As it’s going to stall the production since the time he/she resumes the office.

An example of long terms limitation may be the shortage of chemical mixing machines for a company in a dying industry. While there is sufficient labor to work, sufficient production space, sufficient availability of the raw material, and all other facilities.

However, due to higher time consumption in the mixing machine labour have to sit idle and the capacity of other resources cannot be utilized in full. Hence, chemical mixing machine works as a bottleneck in the process of production.

How to deal with production bottleneck?

An ideal approach to deal with production bottleneck is identifying the bottleneck, evaluating consequences of the bottleneck on production, managing the bottleneck with all the available resources, and increasing production efficiency. Let’s discuss these conceptual aspects to deal with the production bottleneck.

Related article  Price Discrimination - What is it and How Does It Work

1) Identification of bottleneck

The bottleneck can be identified by looking at the accumulation in the production process. It’s the point where units take greater time to be processed, and there are several units in the queue of production.

However, identification by accumulation does not always work. So, a more reliable approach is to use throughput in the production process. The throughput helps to determine the number of units processed by the machine at a specific time.

If there are different machines in production, a comparison of throughput between each machine can help identify the machine that produces the lowest units in a specific time.

Hence, the machine with the lowest production is a specific time is a bottleneck that limits the production of the entire production process.

2) Evaluating the consequences

In the second step, the managers need to understand the consequences of an identified bottleneck. The effects of the bottleneck may be severe depending on the nature of the process.

The business needs to identify the consequences of the bottleneck, whether it’s stalling the production process and the business is delaying the supplies to the customers or any other adverse impact on the operational efficiency of the business.

The bottleneck can actually stall the production as other resources may remain idle to get input from another machine which is a bottleneck.

The delayed production due to bottlenecks may cause inventory to pile up in the warehouses. The company may have to incur additional costs for warehousing due to slow production.

Further, a low production rate may be a cause of motivation for the employees as their remuneration may be linked with the number of units produced.

Related article  Process Costing: What is it and How Does It Work

Hence, bottleneck resource needs to be managed appropriately to ensure enhanced business efficiency.

3) Managing the bottleneck

The severity of the consequence helps to decide what action should be taken to manage the bottleneck. If the consequences are severely adverse, immediate action can be required.

For instance, if the consequence of bottleneck is an inability to meet the customer orders and impairment in the company’s goodwill.

The business may need to manage the bottleneck resource immediately even they have to incur the cost. The bottleneck can be managed by addition to the scarce resource, usage optimization, adequate maintenance of the resource, and any efforts that increase output from the resource.

On the contrary, if the impact of bottleneck resources is not much higher, it may be ignored. Else the cost of resource management may be higher than the benefit obtained.

What causes a production bottleneck?

The production bottleneck can be caused by any process in the chain of processes that takes more time than other processes. It may actually be some resource that is scarce and cannot be purchased easily.

The problem with bottleneck resources is that production cannot be completed without a product passes through/consumers the bottleneck resource.

For instance, three machines A, B, and, C is required to produce a product-A. These machines take 10 minutes, 20 minutes, and 10 minutes to process the product. In working shift of 6 hours 36 units can be processed in the machine A and C.

However, machine B can only process 18 units. Hence, the whole production can only finish 18 units in one shift, and machines A and C remain idle for half of the time as machine B takes double the time to process the product.

Related article  LIFO Reserve: Definition, Formula Example, And How Does it Work

Hence, machine B is a bottleneck that limits the production of the entire chain. In this case, more production time of machine B causes a bottleneck. The bottlenecks can be different in different situations. Hence, business needs to get one more machine B if they want to avoid machine A and C idle time.

However, if the business produces different products and cannot get a new machine, it can prepare the production plan that maximizes the profit.

Profit maximization using bottleneck

To maximize the profit with bottleneck, the business needs to consider contribution generation concerning resource usage. If there are multiple business products, it needs to identify which product has the highest contribution margin by using per unit of the scarce resource.

Once the contribution margin per unit is calculated for all the products, the individual products are ranked high to low contribution margin per unit. This approach makes the business get maximum contribution by using bottleneck/scarce resources.